Location of works: | Bac Ai District, Ninh Thuan Province | |
Length of dam as per center line: | 153m | |
Crest height of main earth dam: | 26.7m | |
Main volume of works: | ||
+ Rock & soil excavating: | 122,365m3 | |
+ Rock & soil filling: | 83,344m3 | |
+ CVC works: | 15,965m3 | |
Duration of works: | ||
+ Commencement: | The fourth quarter of 2006 | |
+ Completion: | The fourth quarter of 2009 |